Showing newest 20 of 34 posts from January 2010. Show older posts
Showing newest 20 of 34 posts from January 2010. Show older posts

Saturday, February 27, 2010

It's a long way to the top

No clouds, but the vehicle's got its head in the ceiling insulation.

This evening I'll get the hinges and pins drilled and installed on the pylons. We'll then roll it outside where there is room to put the hub back in and mount the prop. It will be very cool to see it 95% assembled.

Solve the Ridley

The first steps of the vehicle. (And no, Ridley Scott is not just off camera directing -- it actually rained).



This is the approximate pilot position. We'll have a sling seat between the chassis rails but for the pic I was just using my elbows to keep my jeans off the wet pavement.

Frontal Lobes

I built up the front wheel last night. After the struggle and learning experience of the two custom rear wheels, this one went together really easy. Easy lacing and truing.

This morning I milled, mounted and welded on the tabs 100mm apart on the bottom of the forks. I will work on the brake caliper mounts later -- we won't need brakes nor the steering linkage for the dyno tests one week from now.


Thursday, February 25, 2010

Tower of Power

We spent some fun time this evening with our associate sponsor representative, Dr. Chris Uhlik of Google. He dropped in at a great time with the major components coming together. A few weeks ago all we could have shown him were aluminum shavings.

Here is the thrust box temp mounted on the pylons and standing upright. There are a few gussets that need to be installed before putting the prop on it but it was good to see it in near final form.

That prop hub is 10ft off the slab as it sits there in the picture. It will go up almost another 48" when installed on the chassis.


Wednesday, February 24, 2010

One thrust box to go

Tomorrow evening I'll mount this to the prop stand pylons and then I'll start on the dynomometer. I figure I'll be able to finish most of that project by the end of this weekend. Rick should have all the sensors wired and ready to go for dyno testing the following weekend.

Only a week and a half to go before we spin this puppy up.

The last circle (for now)

I'm tired of making stuff on my mill go round and round (no cnc), but sometimes you just have to grind on through. Until after our initial shakedown testing, this drive sprocket hub should be the last aluminum plate that I turn into dinner plate.




Telemetry through the looking glass

This evening, Rick did final assembly on the telemetry boards that Christian designed for us.

Thanks Christian.

Topping it off

Made the 'thrust box' last night.

The prop shaft will be supported by three bearings mounted to the box bulkheads and will run right through the middle of the box. Cantilevered out from the front end of the box will be the prop hub and to the rear the drive sprocket/spool. Inside the box will be the ratchet hub and the brake rotor. I'll get the bearings mounted this evening and slide the shaft through for alignment.

This box will be sandwiched between the two prop pylons at the very top of the chassis.




Monday, February 22, 2010

Woo Hoo!!

All that component work is gonna pay off soon with an assembled cart.

I ordered the parts for the dynomometer today -- that will be the next project after assembly of the vehicle. The 6.5HP Honda engine will spin the wheels and allow us to test initial mechanical reliablility and also prop behavior at static thrust. Data from the sensors will tell us if at windspeed the vehicle will accelerate or fall back ... a rather important distinction. :-)

Final load cells integrated.

Finished up the outboard bulkhead bearing points -- installed the load-cell brackets (lower right of shiny bearing bracket and also installed the limiting stops on each side.


I'm not going to install the brake caliper brackets until after dyno testing (no need for brakes on the dyno), but other than that this rear assembly is ready to install on the chassis.

Next up -- have to build the cap for the prop stand pylons then mount the prop shaft bearings, brake rotor and rear sprocket before mounting the cap and preparing to mount the prop on the chassis.

Sunday, February 21, 2010

To the back of the bus

Worked on the mounting and assembly of the lower rear of the vehicle this weekend.

Here I'm installing the mid bearing bulkheads:



Bulkheads and bearings in place, along with the brake rotors, ratchet hubs and sprocket cassette.



A shot of the (near) total rear assembly.




A closer look at the 'half-shaft' with the ratchet hub installed and the linear bearing bracket where the drive axle load cell will be installed. I'll get the load cells in there tomorrow evening.

Once the vehicle gets off the dyno, these 'half-shafts' will be replaced with full shafts to widen the vehicle track by about 4ft for more stability in the wind.

Thursday, February 18, 2010

No clearance Clarence

Blades on the hub and balanced. Wish we had room to spin it up -- we're about to pull the chassis back in the shop and start nailing stuff to it. This weekend we'll start that process.




One DDWFTTW vehicle to go please.

It appears we should have ordered our DDWFTTW cart from an online Chinese hobby shop -- our buddy Tim built an entire airplane this evening in the time it took us to install just one prop hub collar.



*$!$% you Tim.

Blow me away

Rick just sent me a shot of the pressure transducers we'll be using for our pitot tubes, and a couple more shots of the telemetry board in process.



The calm before the storm.

This evening we will final assemble the prop hub (sans telemetry), install the blades and balance them.

A final shot of the parts and sub-assemblies of the instrumented hub.


Bones on a stick

Our propeller spar is a tapered carbon shaft. Our dogbone bearings and collar sets are all the same size. We built up 'pads' in the appropriate locations at the spar roots to allow the hub to interface tightly with the spars.

Since our spars were a bit longer than we needed for our 16' propeller, we added an extra set of pads outboard from the design point. By shifting the pads used and thus changing the diameter of the propeller by about 15% we can change the effective twist of the prop from it's design point.

Options are good and we'll test in both locations to see where we get the best results. If the original location is the best, we'll chop that last pad and its 6" of the spar off and discard.



Tiny brains

While I've been turning billet into shavings (and other assorted goodies), Rick has been busy with the instrumentation.

We got our custom PC boards in that our buddy Christian Klippel designed for us (Thanks a bunch Christian) and soon after our components also arrived. Rick went to work under the glass with the surface mount components, tweezers and the soldering iron.



What's your angle?

The last mechanical piece of the propeller hub left to fabricate was the pitch adjusters. These are only adjustable between runs currently, but are positioned such that if we later decide to add run-adjustable pitch we can do so.


Tuesday, February 16, 2010

Hex me

A few weeks ago I made the 'ratchet hubs' that went between the wheels/prop and the transmission. The hubs themselves fit nicely on our aluminum axles (as they were designed to do), but I had to come up with some way to connect the half shafts into the ratchet hub. Tums out that 3/4" hex bar slides nicely into the axles.

I drilled out the hex for weight savings. Also on the prop shaft we may eventually run a control rod through the hollow shaft for variable pitch control. If I didn't also drill the hex out I would be unable to run this control rod through the assembly.


As previously mentioned, my hex bar was 3/4", but my ratchet takes an 11/16" hex head so again a bit of milling to make them match up.



All that is left to do is secure the hex stub inside the shaft on the right. Perhaps a roll pin or two. I'll work on that tomorrow evening.

Thursday, February 11, 2010

Odds and ends

A bit of pickup work this evening -- odds and ends that will allow the final assembly of the prop hub and the installation of the prop spars:

I milled off the tops of the stop and load cell contact bolts. The hub can now freely move fore and aft on the roller even under load. Also adjusted all the stops.



I installed the three load cell over-load limit set screws in the thrust plate. These insure we don't deform the load cells

I drilled, tapped and installed the screws in the prop spar 'dog bones' that hold the bearings in place. These bearings are inset into the bones and generally will be pulled into their sockets -- the screws only hold the bearings in place when not under load.

I also sliced the small bronze sleeves that will act as spacers -- holding the spar collars against the bearings but away from the bones. This will allow the spar to rotate freely for pitch adjustment.