Friday, November 27, 2009

A table for 2x

We've spent the last couple weeks working on our prop design. Rick's got a good handle on that now and we are close to starting construction on the template/ribs/etc. We'll post up some of the airfoil and performance plots in a bit.

Today we spent the day making up our build table. It has to be very straight and square so we can put our reference lines on it and also bolt guides to it etc.

Rick came up with a slick little set of adjustable braces that allow us to take any twist out of the table and still let us fold it up and put it against the wall when we aren't using it.

Here is Rick putting the last screws in the piano hinges before we put the legs on and turn the table over.

Table on it's feet for the first time.

A close up of the little adjustment bracket that I milled slots in. Loosen the wing nuts and slide the triangles relative to each other and the top twists/untwists.

Sunday, November 15, 2009

Turns out we didn't need that.

As previously mentioned, we weren't exactly sure how the torsional stiffness of the chassis would be affected once we got the front steering assembly welded and installed. We suspected we could remove the front former altogether.

Once it was all bolted in we did a torsional load test, removed the front former and repeated the test. There was no difference between the two tests. The welded front assembly provides enough torsional rigidity that the front former is uneeded. Out with it.




Point us in the right direction and turn us loose

Rick and Steve spend Saturday running Java Prop sims on different prop sizes, planforms and airfoils. They're looking for the right balance of RPM and efficiencies that will give us the best transmission/prop combo and also have an airfoil sized right to accept our windsurfing masts as spars.

I spent the day welding and mounting up the steering fork for the front wheel.


The (almost) finished product. I haven't mounted the tabs for the wheel hub because I want to wait until we actually get the hub in our hands. I like to do things only once when possible.



Once we mount up the hub/wheel/tire, we'll decide whether we steer directly with our feet or with a linkage back to a stick.

Thursday, November 12, 2009

Having a busy week at work so there's not much evening activity going on cart wise. We did spend a couple hours last night adding the composites to the center chassis former.

It was going to be a bit of a pain in the ass to use the carbon tow in this short space so we grabbed a few yard of unidirectional carbon fabric and wrapped with that. We again finished over that with one layer of 5.8oz glass to protect the brittle carbon.

Next up ... I'm going to weld up and install the front steering mechanism and wheel support. On it's own this will add some stiffness to the front portion of the chassis and after it's installation we will determine if the front former is just stiff enough, or needs composite layers added, or can be removed completely.




Sunday, November 8, 2009

We build a set of crude headstocks so we could wrap the prop pylons by spinning them. It was a ton easier this way rather than looping the spool around and around like we were forced to do on the chassis itself.

Here's Rick starting the windings.

100 layers of carbon tow on each pylon and a layer of 5.8oz glass later:


Before the wraps we did a torsion test and recorded the results. Once this cures I'll publish the pics showing the before and after tests. Hopefully we added a good bit of stiffness.

Friday, November 6, 2009

We received the 'correct' steering bearings today.

Cheap Chinese bearings are easy on the wallet but sure can be a pain in the a** sometimes. These are supposed to be for a 3/4" shaft, but as you can see the .738 ID is going to require me to do a bit of material removal.

Oh well, 5 minutes work with the grinder and we'll have a .737 steering shaft. :-)


Thursday, November 5, 2009

Tested the sample of Qpower line that we received. Stretch and strength as advertised and as expected. So far the stretch characteristics of Kevlar, Spectra/Dyneema and Vectran have all be similar - well under 1% under our proposed loads.

This product has a thin woven sheath and I feared that this would add a bit of 'squishy' to the end result. I was pleased to find that under load, I could do the usual gentle caliper measurement and then squeeze very hard and only get a .001 or .002 difference. Pretty happy with that as the sheath will up our durability - though it does add another layer on the reel due to the diameter increase.

I'm pretty sure that this line will be the line that we use to test the spool transmission for suitability.



Wednesday, November 4, 2009

The students had a presentation due today relating to the project. I dropped in to catch it in person and on video.

After their 15 minute presentation, they were grilled by other students and the Professor regarding various aspects of the project.

There was a bit of stage fright going on and I can certainly relate.


The bearings arrived for the front steering mechanism. I was waiting for these before welding up the front steering fork and mounting brackets.

I ordered the right bearings and this was reflected on the packing slip --- but they sent the wrong ones. These things happen.

Should have the replacements in by Friday.

Monday, November 2, 2009

Holloween Workothon

A few thousand wraps of carbon tow, a bit of of glass fabric on the bias and a quart or so of epoxy resin later ...




Holloween Workothon

Foam on and ready for carbon/glass wrap.




Holloween Workothon

I worked on cutting and tacking up the parts for the front forks and steering mechanism. The bearings should arrive today so I'm going to wait for them before welding up everything for good. Check twice, weld once as they say.




Holloween Workothon

Dat and Aung worked on cutting, sanding and fitting up the foam to the chassis pieces.




Holloween Workothon

With our layup plan now in place, some of the gang showed up Saturday morning to help with the chores.

Chris helps Rick disassemble the frame in prep for lamination...


... and ends up at the whiteboard talking transmission theory (or some other brainteaser ...with Rick you never know).

Sunday, November 1, 2009

It was testing time for the chassis beam samples that we laminated a few days ago.

First the bare control sample: it weighs 4.5lbs and ~9 degrees of twist. That's a 30lb weight out 24" on the arm.


Next the fiberglass sample: 5.5lbs and ~4 degrees of twist

Finally the fiberglass/carbon combo: 5.7lbs and ~2 degrees twist.


So, it's settled ... will will use the fiberglass and carbon combo. 5.8oz cloth and 70 layers of 12k carbon tow wrapped diagonally.
.
For those of you wondering why we're using the labor intensive tow rather than using carbon fabric, it is mostly because we *have* the tow already -- we paid $60 for 16,000ft of it as potential tranmission line, but it failed for that purpose. Rather than spend near $500 for carbon fabric we will do a little hand wrap work and save both money and weight.

Friday, October 30, 2009

Going in for the easy layup

Aung, Dat, Sheetal and I were up till around midnight last night laying up the torsional test samples. It was quite an adventure as we had to MacGyver a hot wire rig together. Since we have quite a bit of foam cutting ahead, today we'll work on putting together a better wire setup. Aung and I cut this foam by pulling on a wire between us while Dat bravely held the wire to the terminals of an RC starter battery.

The one on the right has just one layer of 3.7oz glass and the one on the left has about 20 diagonal wraps of carbon tow under the same layer of glass. The control is in the center.

Saturday morning they will be cured and we'll test against the control. I'm betting there won't be a dramatic difference between the two and that neither will be stiff enough without another layer. But then, what the heck do I know?



Wednesday, October 28, 2009

We're drillin' for oil

We had our weekly team design meeting today and just so everyone could get a feel for the scale of what we were doing I clamped all the primary chassis pieces together for viewing. When they imagined the tip of the prop another 10ft above the prop pylon, they were better able to see why the cart has the width and length it does. More than one commented that it looked like an oil drilling derrick.

The rear axle cage that you see here is only for dyno testing -- the one used out on the runway will be twice as wide. The prop stand you see there is 12ft high and is sized for a 20ft prop. Those tall pylons will be faired out to a long airfoil shape for low drag. Even at only windspeed, those pylons get a lot of airflow from the wash of the prop so they need to be sleek.

Bob Parks was at our meeting and over the next few days will be helping us determine if we will be building a 20ft prop or one as small as 16ft turning a bit faster. The larger prop is more efficient on it's own, but gearing losses on a slower turning prop can erase those gains. He's going to help us find the most productive balance.

Before we laminate the foam/glass/carbon on our chassis members, we want to build a test fixture and run samples to optimize the layout for best torsional rigidity vs weight.

We will save one of these pictured samples as a control and layup the other three in varying combinations of glass and carbon. We will then test the three for the best stiffness/weight ratio and against the control to see if any of the three give us the improvement we need. If none of the sample are rigid enough, we will go another round of composites over the existing layers and test again.

We hope to have these samples/tests done by the end of this weekend so we can then start layup on the chassis proper.